Resumen: Los primeros vagones eléctricos del Tren México-Pachuca, provenientes de China, ya están en los talleres de Pantaco. El proyecto de 58.12 km conectará la CDMX, el AIFA y Pachuca en 2027.

Creado: 2026-11-10 por

The first electric cars for the Mexico-Pachuca Train have arrived in Mexico. The units, manufactured in China, reached the country as part of the investment for the Felipe Ángeles Train and are being kept in the workshops and depots of Pantaco, in the Azcapotzalco borough of Mexico City, before being moved to Hidalgo for assembly.

  • Arrival of cars: The first electric convoys from China are already at the Pantaco workshops in Azcapotzalco.
  • Total investment: The project calls for the acquisition of 15 trains for the rail corridor.
  • Assembly in Hidalgo: Some of the convoys will be put together in Ciudad Sahagún, where the Chinese company CRRC Zhuzhou Locomotive has rented an industrial warehouse.
  • Planned operation: Service is expected to begin in 2027 with trains carrying up to 718 passengers and a top speed of 120 km/h.

A 58-kilometer corridor linking Mexico City, AIFA and Pachuca

The construction of the Mexico-Pachuca Train is moving forward along a 58.12-kilometer route that will connect Mexico City, the Felipe Ángeles International Airport (AIFA) and the capital of Hidalgo. The project is scheduled to start operations in 2027 and will serve both airport users and residents of the municipalities between the northern Valley of Mexico and Pachuca.

Each train will hold up to 718 passengers and reach a maximum speed of 120 km/h. The Agency for Trains and Integrated Public Transport reported the arrival of the first electric cars, while authorities still plan to purchase 15 trains for the new rail corridor.

On social media, Andrés Lajous, director of the Agency for Trains and Public Transport, shared a video showing details of the first cars that will be part of the Felipe Ángeles Train project. According to authorities, these units will serve the route to Pachuca and will stay at Pantaco for a time before moving to Ciudad Sahagún, where the parts will be assembled.

So far, authorities have not disclosed further details about the trains' features or the construction process.

Ciudad Sahagún, the assembly site for the convoys

The head of Hidalgo's Secretariat of Economic Development, Carlos Henkel Escorza, said the Chinese company CRRC Zhuzhou Locomotive has rented an industrial warehouse in Ciudad Sahagún, where it will assemble a large share of the 15 trains for the Mexico-Pachuca project. The company is headquartered in Querétaro and chose the area for its proximity to the new line, since the cars must be moved there for testing before entering service.

“The company that won the Mexico-Pachuca train project via AIFA is setting up an assembly center in Ciudad Sahagún, since it is headquartered in Querétaro. It rented an industrial warehouse and is starting to assemble,” the state official told the press.

Henkel Escorza said companies based in Ciudad Sahagún are working with the Chinese multinational on prototypes and proposals in the metalworking and fiber-textile sectors. The secretary said they are still waiting to learn which of those firms will be selected.

“What they lead us to understand is that a large part of them, the trains, will be assembled in Ciudad Sahagún; I insist, there are several processes,” he stressed.

The official added that Hidalgo companies have prior experience from working with Alstom and Green Bayer, firms based in the area with national and international projects. According to Henkel Escorza, that activity has prevented a contraction and has generated jobs and economic spillover.

Civil works progress and project layout

In May, authorities reported that civil works had reached an overall progress of 34.80%. By the end of July, the first elevated concrete structures and the so-called whales that will form the future Xaltocan II station were already visible.

In Xaltocan, beams and columns are being installed to support an elevated section over the Circuito Exterior Mexiquense. The installation of these pieces follows the construction of the foundations that must bear the weight of the rail infrastructure. Foundation work and beam assembly also continue at the future Pachuca terminal. The route will be for passengers only.

The line will cross Mexico City, the State of Mexico and Hidalgo. It will have four main stations, four intermediate stops, two viaducts totaling 5.89 kilometers, four electrical substations and more than 51 kilometers of cuts and embankments. Most of the route will use existing rights of way, without requiring the full opening of new corridors.

The Secretariat of National Defense, through the Felipe Ángeles Engineers Group, is in charge of construction. The line will start from the Lechería-AIFA section of the Suburban Train, inaugurated before the Mexico-Toluca Interurban Train. The plan envisions about a year and a half of construction work.

With the arrival of the first cars and progress on civil works, the Mexico-Pachuca Train is entering a key phase of testing and assembly. The challenge for authorities will be to coordinate the manufacture of the 15 convoys, the completion of infrastructure and integration with AIFA before the planned start of operations in 2027.